Most - The renovation of the Repre cultural house in the center of Most is ongoing. All demolition work has been completed, and experts are sanitizing the concrete structures. Builders are encountering unexpected obstacles. After the necessary asbestos removal, they have now discovered a sub-layer of fill. The city’s construction coordinator Matěj Benda told reporters today that he believes the work will be completed by the end of 2026. The costs are approximately one billion crowns.


The demolition work has ended. The sanitization of concrete structures and partially of steel structures is being completed. A roof will be laid on them. "There are many things complicating the work," Benda stated. "Additional surface sanitization is delaying us a lot," he said. In the first underground floor, there was supposed to be a gravel layer under the base. "But there is fill here. Tests were conducted to see how much it could bear. The load tests failed, so the designer is now working on a solution," he said. "It’s about money and time," Benda added.

The original deadline for completion was September 2026. The removal of asbestos increased the total cost of the work by 25 million crowns and the implementation period was extended by 120 days. The building, which was constructed by prisoners in the 1970s, is statically sound, but its execution is catastrophic according to experts. The construction was conducted quickly but unprofessionally, with inaccuracies in the concrete structures and even a bricked-up glove found.

The contractor began the largest contract in the city’s modern history a year ago. The library with an archive will move into Repre, taking up a significant part of the building, a new educational exhibition will be created, and the planetarium and the hall where balls were previously held will be preserved. It will be multifunctional, meaning it can also be used as a cinema. The hall will have a capacity of 800 people. There will be a restaurant on the ground floor. Escape exits must be built, which will require two new staircases, and the building will have 12 elevators.

The Repre cultural house is located in the center near the main street Budovatelů, right next to the town hall. The city sold the property in 2010 for 28 million crowns. An arbitration court declared the sales contract invalid in 2015 and identified Most as the rightful owner. A demolition order had been issued for the building in the past. Some residents of Most opposed the reconstruction of the building without announcing an architectural competition. The city leadership argued that there was no reason for an architectural competition because the appearance of the building would not change.
The English translation is powered by AI tool. Switch to Czech to view the original text source.
0 comments
add comment

Related articles

0 20.03.2026 | Reconstruction of the Repre in Most is very complicated for the builders, the deadline is being extended
0 16.01.2026 | Cultural House Repre in Most will receive a new presentation, repair costs are rising
0 20.10.2025 | The Repre Cultural House in the center of Most will not be repaired by the end of 2026
0 10.04.2024 | In Most, the long-awaited reconstruction of the Repre cultural house has begun
0 05.03.2024 | Most has not yet signed the contract with the supplier for the repair of Repre
0 29.02.2024 | Most releases money for the repair of Repre, opponents of the reconstruction failed to succeed with the protest
0 27.02.2024 | More than 50 people came to express their disagreement with the reconstruction of Repre in Most
0 15.01.2024 | Four candidates applied for the competition to restore the Repre in Most
0 24.08.2023 | The antitrust office canceled the competition for the reconstruction of the Repre house in Most
1 30.07.2021 | The proposal for heritage protection of KD Repre in Most did not succeed
0 03.02.2021 | Most announced a tender for the renovation of the cultural house Repre
0 15.12.2020 | Most will buy the Cascade hotel in the center due to concerns about the hostel
0 01.07.2019 | Most will use the budget surplus for the reconstruction of the cultural center
0 23.11.2017 | The project for the renovation of the cultural house Repre in Most will be created by Artech
0 09.06.2017 | Most announces a tender for the project of renovating the cultural house Repre
0 28.02.2012 | New Cultural House Repre in Most: Demolition instead of renovation