The city will open the promenade along the reservoir in Liberec in December at the earliest

Publisher
ČTK
22.11.2026 10:35
Czech Republic

Liberec

Liberec – The city will reopen the popular promenade along the reservoir in Liberec in December at the earliest. The work is several months behind schedule, and the city will also pay more for improvements to the area around the reservoir—nearly 90 million crowns. City Hall had originally budgeted less than 80 million. According to Deputy Mayor for Architecture and Urban Planning Jiří Janďourek (Mayors for the Liberec Region), the work is entering its final phase.

"Construction work on the first phase of improvements around the reservoir will be completed on Wednesday, November 25. However, we still need to carry out several administrative procedures to ensure everything is legally in order. The area could therefore open to the public in early December," Janďourek said.

Once Phase I is completed, only the section from the dam to the beach will be accessible; it will still not be possible to walk all the way around the reservoir. "As for the second phase, we plan to complete it on December 12. If there are no unforeseen complications, we will follow on seamlessly from the first phase and finish all remaining construction work by that date," the deputy mayor added.

The revitalization of the area around the reservoir follows a renovation of the dam costing more than half a billion crowns, funded by the state-owned Elbe River Basin Authority. The dam's modernization took three and a half years and ended this spring. The city is paying for the improvements to the surrounding area. The original deadline for completing Phase I was late July or early August, with the entire project due to be finished in early October.

There were several complications, but the biggest increase in construction costs came from a former, disused millrace, also referred to as a channel, beneath the promenade. Only after it was uncovered did it become apparent that some sections had no bottom and were structurally unstable. "Concreting the channel cost about six million crowns," Janďourek added.

The area around the reservoir is among the most valuable green spaces in this city of 100,000 residents and is popular not only for leisure activities by the water but also for walking and recreational running. The revitalization is expected to restore more than a kilometer of promenade along the reservoir's right-bank wall. It will connect to a newly built footbridge over Harcovský Stream near Bílý mlýn, providing safer access to Zvolenská Street. The contract also includes laying a sidewalk at the beginning of Zvolenská Street and repairing the paths leading down the steep hill from Blahoslavova and Chelčického streets to the promenade.